Key points
- The line runs Kashgar – Torugart – Makmal – Jalal-Abad – Andijan, about 532.53 km, of which about 312 km in Kyrgyzstan.
- Construction was launched on 27 December 2024; the financing agreement with Chinese banks was signed on 16 December 2025.
- Standard gauge runs from China to Makmal, where cargo changes to 1,520 mm broad gauge for Jalal-Abad and Uzbekistan.
- It is not in service in November 2026; book rail via Kazakhstan or road via Irkeshtam instead.
- Project estimates speak of 700–900 km shorter routes and 7–10 days saved; these are planning figures, not timetables.
- 1Kashgar
- 2Torugart
- 3Makmal
- 4Jalal-Abad
- 5Andijan
Example (hypothetical): a Tashkent importer orders a 40-foot container of household appliances from a factory in eastern China. Below, the container travels the planned line as it is designed. At each leg we note what the same container does today, because that is the route you can actually book.
Where the project stands in November 2026
The idea dates back to a 1997 memorandum. The three governments signed the intergovernmental agreement on 6 June 2024 and launched construction ceremonially on 27 December 2024. A joint company owned 51% by China and 24.5% each by Kyrgyzstan and Uzbekistan builds it; about USD 2.3 billion comes as a 35-year Chinese loan under a financing agreement signed on 16 December 2025, and the rest from the shareholders.
In 2026 the work moved into its active phase. Kun.uz reported active construction in July 2026; UzDaily reported on 28 August 2026 that about 17% of construction was complete by early August, with eight major bridges under way and more than 10,000 workers on site, and that Uzbekistan's transport minister expected the line could be finished at least a year ahead of the original timeline. On 17 October 2026 China's premier Li Qiang and Uzbekistan's President Mirziyoyev discussed speeding up construction in Tashkent. None of this makes the line bookable today.
Leg 1: loading in eastern China and the rail run to Kashgar
Our container is loaded at the factory, sealed, and declared for export in China. It then travels by Chinese rail to Kashgar in south-western Xinjiang. This part exists already and will not change: Kashgar is the railhead for both the planned line and today's road route over the Kyrgyz passes.
Today: from Kashgar, the container either goes onto a truck for Irkeshtam, or it never comes to Kashgar at all and goes north to Alashankou or Khorgos for the rail route through Kazakhstan.
Leg 2: Kashgar to the Torugart border on standard gauge
On the planned line the train climbs from Kashgar to the Torugart pass on standard 1,435 mm track. Torugart is already a road crossing at about 3,750 m on the Kashgar–Naryn–Bishkek road, known for winter weather closures and for being closed on weekends and public holidays. A rail crossing would move cargo across the border without the truck queue, but rail border posts have working patterns of their own, and the rules for this one have not been published.
Customs, as the rules work today: Kyrgyzstan is in the Eurasian Economic Union. A container for Uzbekistan would cross Kyrgyzstan under customs transit and pay nothing there, exactly as a TIR truck does now.
Leg 3: through the Kyrgyz mountains to Makmal
This is the hard part of the project. The Kyrgyz section in the 2026 design has 29 tunnels with a combined length of about 105 km and 50 bridges, and runs about 160 km from Torugart to Makmal. The line is planned as single track, diesel-hauled, for speeds up to 120 km/h, with room for electrification later.
Leg 4: the gauge change at Makmal
Unlike the routes through Kazakhstan, the gauge change on this line does not happen at the Chinese border. Standard gauge runs inside Kyrgyzstan as far as Makmal, where a transshipment complex is planned to move containers onto 1,520 mm wagons, form trains, weigh cargo and transfer rolling stock. From Makmal the track is broad gauge, the same as in Uzbekistan and the rest of the former Soviet network.
For our container this means one lift from wagon to wagon, as at Dostyk today. Where the days are lost at Dostyk (waiting for a full train, wagon supply) is a reasonable guide to what to watch at Makmal once it opens.
Leg 5: Makmal to Jalal-Abad and across into Andijan
From Makmal the line runs about 145 km to Jalal-Abad and then to the Kyrgyz–Uzbek border and Andijan in the Fergana Valley. At Andijan the container is on the Uzbek network, which already connects to Tashkent, and the importer files the Uzbek declaration at the destination post. Uzbek clearance rules do not depend on how the box arrives: the contract, certificates and value file are the same for rail via Kazakhstan, road via Osh or a future train via Makmal.
Today: the closest thing to this leg is rail–road multimodal. Rail to Kashgar, truck over Irkeshtam to Osh, then Uzbek rail from Andijan onward. A 2022 service of this kind, Kashgar–Osh–Andijan–Hairatan, took about 9 days.
What the line changes, and what it does not
- A rail option that avoids Kazakhstan for Fergana Valley and Tashkent cargo
- Project estimates of about 700–900 km shorter routes and 7–10 days saved on some flows
- Long-term design capacity of about 15 million tonnes a year
- Less exposure to truck queues and mountain road closures
- One gauge change still happens, at Makmal instead of Dostyk
- Customs transit across Kyrgyzstan and clearance in Uzbekistan
- Certificates, labels and the value file Uzbek customs asks for
- Seasonal weather in the mountains, now for a railway
Until the line opens, the choice for Uzbekistan is between rail through Kazakhstan, typically about 10–18 days from eastern China to Tashkent station to station, and road through Kyrgyzstan, typically about 10–16 days door to door. Golden Way ships from China to Central Asia by rail and road via Khorgos, and our team will quote the route that suits the cargo within one working day.
Check the facts
Frequently asked questions
When will the China–Kyrgyzstan–Uzbekistan railway open?
No opening date for freight has been fixed. Kyrgyzstan's president spoke of completion around 2030 in March 2026, and Uzbekistan's transport minister said in August 2026 it could be finished at least a year ahead of the original timeline. Treat any date as a target, not a schedule.
Will it replace the rail route through Kazakhstan?
It adds a second rail option to Uzbekistan and the Fergana Valley. The Kazakh route serves many other destinations, and its own capacity is growing, so both are expected to be used.
Will freight rates be lower on the new line?
No tariffs have been published. A shorter distance helps, but rates depend on the railways' tariffs, the gauge change at Makmal and demand, so it is too early to say.
Is the line important for Afghanistan cargo?
Cargo to Afghanistan through Uzbekistan crosses at Termez–Hairatan. A shorter rail path from China into the Fergana Valley could feed that route, but every Afghanistan shipment still goes through our compliance review.
Does Kyrgyzstan collect customs on goods passing through to Uzbekistan?
Under today's rules, no. Goods cross Kyrgyzstan under EAEU customs transit and are cleared in Uzbekistan.
Sources
- UzDaily: China–Kyrgyzstan–Uzbekistan railway construction progresses ahead of schedule (28 Aug 2026)
- Kun.uz: China–Kyrgyzstan–Uzbekistan railway project enters active construction phase (13 Jul 2026)
- CGTN: Chinese premier says Beijing ready to ensure high-quality China–Kyrgyzstan–Uzbekistan railway (18 Oct 2026)
- Wikipedia: China–Kyrgyzstan–Uzbekistan railway (route, gauge, tunnels, financing)
- Times of Central Asia: Uzbekistan, Kyrgyzstan, China now have shortest motor transport corridor
- Eurasianet: Cargo leaves China for Afghanistan on new route via Kyrgyzstan, Uzbekistan (2022)